{{featured_button_text}}

CARLIN – While other mines are holding steady or cutting back, Newmont Mining Corp.’s Leeville Underground is ramping up production and hiring more people.

The mine commissioned the Turf No. 3 Ventilation Shaft in November, said Veronica Tough, chief engineer for Leeville.

When the underground only had two shafts, the No. 1 shaft was exhaust — hot and humid air — and the No. 2 shaft was intake. The new system and No. 3 shaft allows both of those to be intake, she said. The air flow direction changed on the No. 1 shaft and the No. 2 shaft kept the same direction but the quantity of air through it changed, Tough said.

Prior to the new system, the mine had 1.2 million cubic feet per minute of air through the mine. Now Leeville is at 1.9 million CFM.

“So the volume increased,” Tough said. “I would say the big change is the ventilation system prior was set up to mine the areas that we had at the time. … The new vent shaft allows much fresher and more volume of air down to the area where we’re doing a lot of the work.”

Complaints from the miners used to be it was too hot to work and now they’re complaining that it’s too cold or too windy, she said.

The new shaft will allow Newmont to explore more underground.

“Prior to putting in the new shaft, ventilation was our limiting factor for how much we could produce, how much drift we could drive, how far we could get away from our main infrastructure,” Tough said.

The new shaft allows Leeville to ventilate in areas it couldn’t before.

“The big justification to the shaft was being able to bring more equipment into the mine and mine at a higher pace,” Tough said. “Between the three groups — engineering, maintenance and operations — we’re adding over 100 people over the next year to the workforce, and that’s just our people. We’ve got contractors too, that we’ll be bringing in to help us out. It’s a huge benefit for the economy. You look at a lot of other sites are ramping down and we’re ramping up. So it’s a very unique position and a good place to be with the gold prices the way they are.”

Maintenance

Albert Keim, maintenance superintendent, said the new system, “in some aspects,” makes the maintenance more complicated.

“In order to make this change underground, we had to install, just for the commissioning portion, roughly 40 bulkheads, air doors and booster fans,” Keim said. “So that means just more maintenance on those bulkheads, or those structures. But for moving the fans from underground to surface, the conditions that they’re in, it’s more acceptable. You don’t have to deal with ground conditions, ground movement, mine sap getting in your blades and stuff like that. Everything is located on the surface now. They’re a lot easier to work on.”

The technical name for mine sap is “Copiapite” which is naturally occurring at Leeville, he said.

Keim said having redundancies for the ventilation system also helps. When there were only two fans, it limited production underground at times.

“Before we had two main fans that had to be running all the time in order for us to provide the mine with enough air,” he said. “Now we have four fans. At this time, two are off – one’s in maintenance repair at all times and one’s a backup at all times. So we have redundancy now, so that’s a definite benefit.”

Keim said the ventilation is operated by the hoist house at Leeville. The operator can start and stop fans.

History of the Project

Designing for the project started in 2010 and construction began in 2012, said Craig Gammill, construction manager for the project group. At the height of construction it employed 160 people. The project was a $360 million investment for Newmont.

When the shaft was under construction, it was sunk through conventional means, but the ground was in an unusual state, because it had to be frozen. The shaft was sunk through an aquifer — 400 feet down to 1,800 feet was saturated — so the freezing allowed the construction crews to control the drilling.

As the shaft was drilled, construction crews poured concrete every 15 feet, Newmont stated previously.

The shaft also has a conveyance feature, Gammill said.

“The unique feature that’s associated with the hoisting set up over here is an airlock for the conveyance to enter and exit the shaft without interruption to the ventilation flows,” he said. “So that was also an opportunity that we took advantage of, by sealing the shaft, starting the fans and then completing the headframe and airlock construction afterwards.”

The airlock will allow access to the shaft for conveyance and inspections.

“We’re currently in the process of commissioning that hoisting system now,” Gammill said.

“Between the three groups — engineering, maintenance and operations — we’re adding over 100 people over the next year to the workforce.” — Veronica Tough, chief engineer

Subscribe to Breaking News

* I understand and agree that registration on or use of this site constitutes agreement to its user agreement and privacy policy.
0
0
0
0
0

Load comments